Maintenance Infrabel Ghent

Project Description

The maintenance contract encompasses the renewal of tracks and point switches, including the clean-up of bedding rubble for primary and secondary tracks. The project comprises 9 sub-tasks involving the renewal of point switches, finishing the site, concrete trenches and concrete footpaths at the following locations:

  • Sint-Niklaas
  • Kerrebroek – Aalst
  • Schellebelle
  • Roeselare
  • Sint-Katharina
  • Wondelgem
  • Kuurne
  • Zelzate

Project Details

  • WerfMaintenance contract Infrabel Ghent – District Northwest
  • BouwheerInfrabel Ghent
  • OpdrachtgeverInfrabel Ghent
  • GebruikerInfrabel Ghent
  • PlaatsGhent - District Northwest
  • Bedrag€ 3,103,831.51
  • Data2014 > 2016
  • SP / KR / W6,584m track - 29 point switches