Stora Enso

Project Description

Each year, Stora Enso Langerbrugge manufactures 555,000 tons of newspaper and magazine paper on the basis of 100% recycled paper. FDP installed the tracks in the new factory. This included the following work:

  • Installation of tracks on ballast
  • Installation of tracks in concrete
  • Installation of tracks in asphalt
  • Supply and installation of 9 point switches, including electrical controls
  • Supply and installation of 9 buffer constructions

Project Details

  • WerfStora Enso
  • BouwheerStora Enso
  • OpdrachtgeverStora Enso
  • GebruikerStora Enso
  • PlaatsWondelgemkaai - Ghent
  • Bedrag€ 3,089,729.90
  • Data2002 - 2004
  • SP / KR / W3,481m track - 9 point switches